Question

13-13 Sid Davidson was able to determine the activity times for the leadership training program. He would like to determine the total project completion time and the critical path. (See #13-12) The activity times appear in the following table: ACTIVITY TIME (DAYS) A 2 B 5 C 1 D 10 E 3 F 6 G __8__ 35

 