Consider the network in problem 6, but with the following new time estimates for each activity: time estimates (mo) Activity a m b 1 4 8 12 2 6 10 15 3 2 10 14 4 1 4 13 5 3 6 9 6 3 6 18 7 2 8 12 8 9 15 22 9 5 12 21 10 7 20 25 11 5 6 12 12 3 8 20 Determine the following: a. Expected activity times b. Earliest activity times c. Latest activity times d. Activity slack e. Critical path f. Expected project duration and variance

 