You are the project manager of a home improvement project. One of the work packages in your plan called for painting 10 equally sized rooms. The budgeted cost of this work package was a total of $2,000. In your team meeting you are told that 6 of the rooms have been painted. What is the earned value (EV) of the work completed?;Additional Requirements;Level of Detail: Only answer needed

 