Details of this Paper

11. 10 consider the project information given in table 11.17 ? A+ Answer or MONEY BACK GUARANTEED!

Description

solution


Question

Network Chart;Part a Project Cost;Activity;Cost;A;3000;B;7200;C;2000;D;7000;E;4000;F;3000;Total 26200;Part b Cash Flows in case of Late start;Week;Activity Run;Cash flow for all activities run during the week (Proportion of total cost of activity);Cumulative cash flows;1;A,B;2200;2;A,B;4400;3;A,B;6600;4;B,C,D;9800;5

 

Paper#21037 | Written in 18-Jul-2015

Price : $27