11.5 for the project data given in table 11.13, assuming an overhead of?A+ Answer or MONEY BACK GUARANTEED!

Description

solution


Question

Activity;Immediate predecessors;Duration;Cost;Duration;Cost;A;-;4;$100;2;$300;B;-;3;$200;1;$200;C;A,B;2;$50;1;$100;D;A,B;3;$100;2;$300;E;A,B;4;$150;1;$400;F;OR;OR

 