Dalton Construction Co. contracted to build a bridge for $5,000,000

Description

solution


Question

Percentage-of-completion method.;Dalton Construction Co. contracted to build a bridge for $5,000,000. Construction began in 2010 and was completed in 2011. Data relating to the construction are;2010 2011;Costs incurred $1,650,000 $1,375,000;Estimated costs to complete 1,350,000 ?;Dalton uses the percentage-of-completion method.;Instructions;(a) How much revenue should be reported for 2010? Show your computation.;(b) Make the entry to record progress billings of $1,650,000 during 2010.;(c) Make the entry to record the revenue and gross profit for 2010.;(d) How much gross profit should be reported for 2011? Show your computation.

 