You?ve just completed a pilot run of 10 units

Description

solution


Question

You?ve just completed a pilot run of 10 units of a major product and found the processing time for each unit was as follows;Unit Number Time (hours);1 970;2 640;3 420;4 380;5 320;6 250;7 220;8 207;9 190;10 190;a. According to the pilot run, what would you estimate the learning rate to be?;b. Based on a, how much time would it take for the next 190 units, assuming no loss of learning?;c. How much time would it take to make the 1,000th unit?

 