Details of this Paper

2-41 The time to complete a construction project is

Description

solution


Question

2-41 The time to complete a construction project is normally distributed with a mean of 60 weeks and a standard deviation of 4 weeks.;(a) What is the probability the project will be finished in 62 weeks or less?;(b) What is the probability the project will be finished in 66 weeks or less?;(c) What is the probability the project will take longer than 65 weeks?

 

Paper#33255 | Written in 18-Jul-2015

Price : $32