The following activities are part of a project to be scheduled

Description

solution


Question

The following activities are part of a project to be scheduled using CPM;Activity Immediate Predecessor Time(Weeks);A -- 6;A 3;C A 7;D C 2;E B, D 4;F D 3;G E,F 7;a. Draw the network;b. What is the critical path?;c. How many weeks will it take to complete the project?

 