Schedule the following activities using CPM:

Description

solution


Question

4. Schedule the following activities using CPM;Activity Immediate Time;Predecessor (Weeks);A -- 1;B A 4;C A 3;D B 2;E C, D 5;F D 2;G F 2;H E, G 3;a. Draw the network;b. What is the critical path?;c. How many weeks will it take to complete the project?;d. Which activities have slack, and how much?

 