A construction project is broken down into

Description

solution


Question

A construction project is broken down into the following 10 activities;Activity Immediate;Predecessor Time (Weeks);1 -- 4;2 1 2;3 1 4;4 1 3;5 2, 3 5;6 3 6;7 4 2;8 5 3;9 6, 7 5;10 8, 9 7;a. Draw the network diagram;b. Find the critical path.;c. If activities 1 and 10 can't be shortened, but activities 2 through 9 can be shortened to a minimum of one week each at a cost $10,000 per week, which activities would you shorten to cut the project by four weeks?

 