Assume that Product Z is made of two units of A and four units of B. A

Description

solution


Question

Assume that Product Z is made of two units of A and four units of B. A is made of three units of C and four D. D is made of two units of E. Lead times for purchase or fabrication of each unit to final assembly are: Z takes two weeks, A, B, C, and D take one week each, and E takes three weeks. Fifty units are required in Period 10. (Assume that there is currently no inventory on hand of any of these items.;a. Show the bill of materials (product structure tree).;b. Develop an MRP planning schedule showing gross and net requirements and order release and receipt dates.

 