The following table gives the operation times and due

Description

solution


Question

1. The following table gives the operation times and due dates for five jobs which are to be processed on a machine. Assign the jobs according to the shortest operation time and calculate the mean flow time.;Job Processing Time (days);101 6;102 7;103 4;104 9;105 5

 