Given the following information about staging a community play on

Description

solution


Question

Given the following information about staging a community play on Independence day.;a. Construct a PDM / CPM diagram;b. Determine the earliest completion time for the play and the critical path.;c.Based on the critical path, what completion date ar you 80% confident of achieving? 40% confident?;d. Will a 1-day delay in this project be serious?;Activity Predecessor Time (days);a m b;1 - 2 4 6;2 - 5 5 5;3 2 3 5 7;4 1 7 10 13;5 1 11 12 13;6 2,4 5 6 7;7 3 9 10 11;8 3,6 5 7 9;9 4 7 9 11;10 5 3 3 3;11 7 15 17 19;12 8 6 8 10;13 9,10 7 8 15;14 7 12 14 16;15 12,13 16 17 18

 