You have signed a contract to complete the project described

Description

solution


Question

You have signed a contract to complete the project described in Table 11.17 within 10 weeks. The weekly managerial fee is $2,000.;a. Generate the schedule that will delay expenses to the last possible moment and indicate its associated cash flow.;b. Generate the cash flow requirement resulting from the objective to increase the probability that the project will be completed on schedule.;Attachment Preview;Table 11.17.xls;Table 11.17;Activity;A;B;C;D;E;F;Immediate;predecessors;A;A;C,B;B;Expected Time;(weeks);3;6;2;7;1;3;Normal cost Expediting cost per;($);week($/week);3,000;1,500;7,200;1,000;2,000;2,000;7,000;2,000;4,000;3,000;1,500;Minimum time;(weeks);2;4;1;3;1;2

 