For the project data given in Table 11.13, assuming an overhead of $350

Description

solution


Question

For the project data given in Table 11.13, assuming an overhead of $350 per period, find the minimum cost schedule. What are the critical activities? How much total slack and free slack exist for the noncritical activities? Find the cost of the early-start and late-start schedules.

 