Generate the early-start resource profile for the two projects.

Description

solution


Question

a. Generate the early-start resource profile for the two projects.;b. Schedule the two projects so that the required labor profile will be as level as possible.;c. Discuss the significance of the differences observed in the schedules found in parts (a) and (b).;Attachment Preview;Table 10.5.xls;Table 10.5;Activity;A;B;C;D;E;F;G;H;I;J;Immediate;predecessors;A;A;B;C;D;F;D,E,G;-;Time;(weeks);4;2;6;3;10;2;5;7;1;10;Crew;size;4;5;3;7;6;5;6;2;8;2

 