Details of this Paper

The precedence relations and crew size required to complete a project

Description

solution


Question

The precedence relations and crew size required to complete a project are given in Table 10.5. For example, activity E, which comes after activity C, requires 10 weeks for its completion by a crew of six people.;a. Construct an early-start Gantt chart and identify the critical path.;b. Calculate and chart the labor profile required to complete the project for both an early-start and late-start schedule.;c. Level the required labor as much as possible with the goal of completing the project within the time period specified in part (a).;Attachment Preview;Table 10.5.xls;Table 10.5;Activity;A;B;C;D;E;F;G;H;I;J;Immediate;predecessors;A;A;B;C;D;F;D,E,G;-;Time;(weeks);4;2;6;3;10;2;5;7;1;10;Crew;size;4;5;3;7;6;5;6;2;8;2

 