The risk-free rate of return is currently 5 percent and the market risk premium is 4 percent. The beta of a project under analysis is 1.4, with expected net cash flows estimated to be $1,500 per year for five years. The required investment outlay on the project is $4,500. What is the required risk-adjusted return on the project? Should the project be purchased?

 