Description of this paper

United Research Associates (URA) received a contract to produce

Description

solution


Question

Question;United Research Associates (URA) received a contract to produce two units of a new cruise missile guidance control. The first unit took 4,000 hours to complete and cost $30,000 in materials and equipment usage. The second took 3,200 hours and cost $21,000 in materials and equipment usage. Labor cost is charged at $18 per hour.The prime contractor has now approached URA and asked to submit a bid for the cost of producing another 20 guidance controls. Refer to Exhibit 4A.5 and Exhibit 4A.6.a. What will the last unit cost to build?b. What will be the average time for the 20 missile guidance controls?c. What will be the average cost per guidance control for the 20 in the contract?Other Requirements: Solution: (I have the solution but i need the steps for undestand the problem. Please show me step by stepa. Cost of 22nd unit = $32,732.40b. 1,886 hoursc. Average cost = $43,126.50;********************************************************************************Part aplease see the attachment************************************************************************Part b please see the attachment

 

Paper#45942 | Written in 18-Jul-2015

Price : $19
SiteLock