Details of this Paper

BA323 - Ch4 quiz

Description

solution


Question

Question;? Question;1;1 out of 1 points;An alternative approach to project crashing is to use which;of the following techniques?;? Question;2;1 out of 1 points;Consider a project that has an expected completion time of;50 weeks and a standard deviation of 9 weeks. What is the probability that the;project is finished in 57 weeks or fewer? (Round to two decimals.);? Question;3;1 out of 1 points;Figure 12-1;Given the network in Figure 12-1, the critical path is;? Question;4;1 out of 1 points;Figure 12-1;Given the network shown in Figure 12-1 and the following;information, what is the variance of the critical path?;Answer;Selected;Answer;9;Correct Answer;9;? Question;5;1 out of 1 points;Figure 12-1;Given the network shown in Figure 12-1, assume that;completion of B is delayed by two days. What happens to the project?;? Question;6;1 out of 1 points;Given an activity's optimistic, most likely, and pessimistic;time estimates of 4, 6, and 14 days respectively, compute the PERT expected;activity time for this activity.;? Question;7;1 out of 1 points;Given an activity's optimistic, most likely, and pessimistic;time estimates of 4, 14, and 18 days respectively, compute the PERT expected;activity time for this activity.;? Question;8;1 out of 1 points;Given an activity's optimistic, most likely, and pessimistic;time estimates of 4, 12, and 18 days respectively, compute the PERT variance;for this activity.;? Question;9;1 out of 1 points;Given an activity's optimistic, most likely, and pessimistic;time estimates of 3, 7, and 11 days respectively, compute the expected time for;this activity.;? Question;10;1 out of 1 points;Given an activity's optimistic, most likely, and pessimistic;time estimates of 1, 9, and 23 days respectively, compute the PERT expected;activity time for this activity.;? Question;11;1 out of 1 points;Given the following small project, the critical path is;days.;? Question;12;1 out of 1 points;In PERT analysis, the probability of the optimistic time;occurring should be on the order of ________.;? Question;13;1 out of 1 points;In a PERT network, the earliest (activity) start time is the;? Question;14;1 out of 1 points;Managers use the network analysis of PERT and CPM to help;them;? Question;15;1 out of 1 points;PERT assumes that the total completion time of a projects;follows which of the following probability distributions?;? Question;16;1 out of 1 points;PERT stands for ________.;? Question;17;1 out of 1 points;Slack time in a network is the;? Question;18;1 out of 1 points;Table 12-1;The following represents a project with know activity times.;All times are in weeks.;Using the data in Table 12-1, what is the latest possible;time that C may be started without delaying completion of the project?;Answer;Table 12-1;The following represents a project with know activity times.;All times are in weeks.;Using the data in Table 12-1, compute the latest finish time;for activity E.;? Question;20;1 out of 1 points;Table 12-2;The following represents a project with four activities. All;times are in weeks.;According to the data in Table 12-2, what is the minimum;expected completion time for the project?;? Question;21;1 out of 1 points;Table 12-2;The following represents a project with four activities. All;times are in weeks.;According to Table 12-2, there are four activities in the;project. Assume the normal distribution is appropriate to use to determine the;probability of finishing by a particular time. What is the probability that the;project is finished in 16 weeks or fewer? (Round to two decimals.);Answer;? Question;22;1 out of 1 points;Table 12-3;According to Table 12-3, there are five activities in a PERT;project. What is the variance of the critical path?;? Question;23;1 out of 1 points;Table 12-4;The following represents a project with known activity;times. All times are in weeks.;Using the data in Table 12-4, what is the minimum possible;time required for completing the project?;? Question;24;1 out of 1 points;Table 12-4;The following represents a project with known activity;times. All times are in weeks.;Using the data in Table 12-4, compute the slack time for;activity D.;? Question;25;1 out of 1 points;Table 12-4;The following represents a project with known activity;times. All times are in weeks.;Using the data in Table 12-4, determine the latest time;activity A can be started without delaying the project completion.;4;? Question;26;1 out of 1 points;The crash time of an activity represents;? Question;27;1 out of 1 points;Table 12-5;How long could Table 12-5's activity F be delayed without;delaying the project?;? Question;28;1 out of 1 points;The project described by;has a critical path of length of ________.;? Question;29;1 out of 1 points;The expected time in PERT is;? Question;30;1 out of 1 points;The two common techniques for drawing PERT networks are

 

Paper#53442 | Written in 18-Jul-2015

Price : $25
SiteLock