Details of this Paper





ID: Task List: Duration: Predecessors;1 Preparation;2 Get trash bags 5 min;3 Pick up trash 15 min 2;4 Put gas in the equipment 5 min;5 Get the hedge clippers 5 min;6 Do the work;7 Trim weeds 30 min 3,4;8 Mow front yard 45 min 3,4;9 Edge sidewalk 15 min 3,4;10 Trim Hedge 30 min 5;11 Mow back yard 30 min 8;12 Clean up;13 Bag grass 30 min 7,9,10,11;14 Bundle trash 15 min 7,9,10,11;15 Haul trash 45 min 13,14;This exercise consists of a list of tasks for a home yard project. Working in Microsoft Project, you will create the task list, including summary tasks and their sub-tasks, create links between tasks and their predecessors. Set a start date for your project of April 30, 2013. Enter the following tasks, including the duration, where specified. Tasks with unspecified duration are summary tasks and the rest are sub-tasks