8. The following represents a project that should be scheduled using CPM:

Description

solution


Question

8. The following represents a project that should be scheduled using CPM;Times (DAYS);Activity Immediate Predecessors a m b;A. - 1 3 5;B - 1 2 3;C A 1 2 3;D A 2 3 4;E B 3 4 11;F C,D 3 4 5;G D,E 1 4 6;H F,G 2 4 5;a. Draw the network.;b. What is the critical path?;c. What is the expected project completion time?;d. What is the probability of completing this project within 16 days?

 