Air Manufacturing uses job costing and reports the...

Description

Solution


Question

Air Manufacturing uses job costing and reports the following amounts for 2012: Budgeted Actual Overhead cost $9,000,000 $9,007,000 Direct labor cost $7,200,000 $7,172,000 Direct materials cost $4,400,000 $4,554,000 Machine hours 250,000 238,100 The following is reported for job 909: Direct labor cost $421,700 Direct materials used $258,440 Machine hours 14,230 If direct labor cost is used as the activity base for assigning overhead to jobs, calculate the total cost of job 909. If machine hours is used as the activity base for assigning overhead to jobs, calculate the total cost of job 909.

 